FROM DESIGN TO COUNCIL DECISION
Prepare a stronger planning application.
Know which form to choose, what drawings and evidence to prepare, how to check fees and what happens after a council validates the application.
Authority rules vary by location · No online application or approval services on this site
What matters first
Plan the route before paying an application fee
A planning application is more than an online form. The correct application type, location plan, drawings, certificates and supporting reports affect whether the authority can validate it.
- 01Confirm permission type
Decide whether you need householder, full, outline, change-of-use, listed building, prior approval or another consent. Ask the authority if uncertain.
- 02Review policies and site designations
Search the local plan, nearby application decisions, flood and heritage constraints, protected trees and relevant guidance.
- 03Consider pre-application advice
Many authorities offer paid or free pre-application services. The response may help identify issues, but it is not planning permission.
- 04Prepare drawings and statements
Use the authority’s national and local validation requirements; drawings should match descriptions and show accurate site boundaries.
- 05Apply and pay through the correct channel
Use the official England/Wales, Scotland or Northern Ireland submission route and follow ownership notices and application certificates.
- 06Check validation and consultation
Keep the reference number, respond to missing information promptly, review representations and monitor the council’s determination.
- 07Read the issued decision
Check approved drawing versions, pre-commencement conditions, decision time limits and any separate building control or consent requirements.
Choose the correct official submission service
- EnglandPlanning Portal application process and appropriate authorityOfficial guidance ↗
- WalesWelsh Government guidance; local authority application routeOfficial guidance ↗
- Scotlandmygov.scot instructions and ePlanning ScotlandOfficial guidance ↗
- Northern IrelandNI Planning Portal; note Mid Ulster’s separate serviceOfficial guidance ↗
Application document checklist
Not every scheme requires every item below. A complex or sensitive site may require more than a basic householder application. Check the local planning authority’s current validation list before paying.
Preparation tracker
Tick items as you gather them. Checks are not saved or sent to us.
0 of 8 preparation steps checked
Understand the cost beyond the application fee
The application fee is only one part of the possible cost. Architectural drawings, surveys, specialist reports, planning agents and charges associated with submission can be significant. The actual prices depend on the location and project. We do not publish a made-up “national average fee”.
Your own planning preparation budget
Enter quoted amounts in pounds sterling. This local worksheet is not a current planning-fee database and excludes construction costs.
Only your own figures are added. Confirm VAT, exemptions, local application charges and the scope of every quote separately.
What happens to a valid application?
Decision timeline: illustrative steps
- 1 Validation
- 2 Publicity
- 3 Consultation
- 4 Assessment
- 5 Decision
In England, the published statutory determination period is generally eight weeks for most non-major applications and 13 weeks for major development, subject to qualifications and agreed extensions. These are not guaranteed delivery dates. Other UK systems have different rules; check your authority.
| Stage | What to check | Why it matters |
|---|---|---|
| Validation | Written confirmation that the submission is valid, date and application number. | The decision timetable normally relates to a valid application, not your first upload. |
| Consultation | Site notice/notification, consultations and public comments. | The authority must consider relevant planning policy and representations. |
| Assessment | Case officer questions, requested information and any amended plans. | Unresolved issues can affect timing or the outcome. |
| Decision | Approval, conditions, refusal reasons and adopted plan/policy references. | Your next actions depend on the signed decision notice. |
| After approval | Pre-commencement conditions, lawful commencement, building control and discharge requirements. | Approval does not necessarily authorise immediate building work. |
After permission is issued: do not miss the conditions
- Read the entire written decision notice, including the specific approved drawings and supporting plans.
- Identify conditions that must be discharged before work begins, before occupation or by another trigger.
- Keep evidence of formal approvals of details where a condition requires submission to the council.
- Confirm whether building regulations approval and other consents are still outstanding.
- Track lawful commencement and completion deadlines set by the permission, not a generic internet article.
- If the design changes, ask whether non-material amendment, variation or a fresh permission is needed.
Questions applicants often miss
What is a local validation list?
It is the planning authority’s requirements for the documents and information needed to accept certain applications as valid. Always use the current list for the relevant authority and application type.
Can I submit without owning the land?
In some circumstances, yes, but specific ownership certificates and notices are required. A planning grant does not give you ownership or permission to enter the land.
Is pre-application advice binding?
Usually not. It can inform the approach, but the formal application and authority’s decision remain necessary where planning permission is required.
What if the planning officer asks for amended drawings?
Confirm exactly which drawings replace earlier versions and how to upload them. Keep the instruction and ensure your final approved plans are consistent.
Primary sources & verification notes
Use the linked guidance to confirm current rules. The responsible council or planning authority has the facts about your location, design constraints and any restrictions that apply to your property.
Reference links reviewed for this publication on 25 November 2026. This is not an audit of every council page or a live status feed.
Received a decision?
Understand refusal reasons, conditions, objections and the appeal routes.